Overburden removal , mining A1,A2 , A3 layers & screening A2 layers in dragline Eshidya
- Project Name : Overburden removal , mining A1,A2 , A3 layers & screening A2 layers in dragline Eshidya
- Location of Project : Eshidya Mine
- Client : Jordanian Phosphate Company (JPMC)
- Awarded date of Project : 4-2018
- Quantities of Project :
- Overburden Removal (OB ) quantities = 22.5 Million BCM
- Mining Phosphate (A1 , A3 ) quantities 3.8 Million BCM ( Storage )
- Inter waste (IW1 , IW2 ) removal quantities = 97 Million BCM
- Mining Phosphate (A2) quantities = 66 Million BCM
- Screening & Crushing (A2) quantities = 14 Million ton
- Completion = 100 %
- Scope of Work:
- Overburden & Internal waste Removal using excavator & wheal loader and transport the OB to the waste yards and cleaning with dozing.
- Phosphate Mining layers A1 & A2 & A3 Cleaning by graders and dozers.
- Transportation using dump truck to screen unit (A2).
- Crushing & Screening A2 Quantities
- Operate (closed vibrating plant system) which high by max. the yield and min. rejection.
- Feeding 50cm hopper by wheel loaders & dump trucks
- Classification / separation of materials by grizzly
- Crushing & sizing the materials to pass 100% of -6mm & -4mm
- All materials handled by conveyor belts
- Transport product to banker then go to stacker then dispatching
- Mixing & blending the product to get the required homogenous
- Hauling the oversize (reject) material to waste yards (Stockpiles) and dozing
All productivity maintenance activities of conveyor belts and vibrating screens plants performed by in house team .